{"id":2750,"date":"2023-06-02T05:50:10","date_gmt":"2023-06-02T05:50:10","guid":{"rendered":"https:\/\/fantaseaplus.com\/?p=2750"},"modified":"2024-05-07T04:32:34","modified_gmt":"2024-05-07T04:32:34","slug":"monthly-construction-update-fantasea-condo-kamala-may-2023","status":"publish","type":"post","link":"https:\/\/fantaseaplus.com\/2023\/06\/02\/monthly-construction-update-fantasea-condo-kamala-may-2023\/","title":{"rendered":"Monthly Construction Update Fantasea Condo Kamala (May 2023)"},"content":{"rendered":"

[vc_row][vc_column][vc_column_text]Welcome back to our monthly construction update for Fantasea Condo Kamala! We are excited to share the latest developments and progress made during the month of May 2023. In this blog post, we will provide you with an overview of the ongoing construction activities and updates on the piling phase.<\/p>\n

<\/span>Piling Progress<\/h2>\n

[\/vc_column_text][vc_single_image image=”2752″ img_size=”full” alignment=”center”][vc_column_text]We are pleased to inform you that the piling work for Fantasea Condo Kamala commenced on May 17, 2023. The piling process is a crucial step in ensuring the stability and support of the condo building. Our team has been working diligently to meet the construction timeline, with a scheduled completion date set for June 15, 2023.<\/p>\n

<\/span>Building A<\/h2>\n

For Building A, the pile pins are currently at 65.00% completion, indicating significant progress. The pile work is at 12.35%, demonstrating steady advancement as we lay the foundation for this remarkable structure.<\/p>\n

<\/span>Building B<\/h2>\n

[\/vc_column_text][vc_single_image image=”2753″ img_size=”full” alignment=”center”][vc_column_text]In the case of Building B, the pile pins have also reached 65.00% completion, mirroring the progress of Building A. The pile work for Building B has made remarkable strides, currently standing at 61.11%.<\/p>\n

<\/span>Mitigating Construction Challenges<\/h2>\n

We encountered some construction challenges and weather-related delays during the month. However, we promptly addressed these issues by deploying additional manpower and employing advanced boring\/drilling machines. This proactive approach has helped us overcome the obstacles and ensure that the construction remains on track.<\/p>\n

<\/span>Detailed Monthly Report<\/h2>\n

[\/vc_column_text][vc_single_image image=”2754″ img_size=”full” alignment=”center”][vc_column_text]For a more comprehensive understanding of the construction progress, we have prepared a detailed monthly report for May 2023. This report includes specific information on the piling phase, milestones achieved, challenges faced, and the measures taken to mitigate delays. We encourage you to review the report for a comprehensive update on the project\u2019s status.<\/p>\n

<\/span>Continuous Monitoring<\/h2>\n

As always, we are dedicated to closely monitoring the construction progress of Fantasea Condo Kamala. Our team is committed to providing you with timely updates and ensuring that the project stays on schedule. We value your trust and aim to deliver a development that surpasses your expectations.<\/p>\n

<\/span>Stay Connected<\/h2>\n

To stay informed about the latest news and updates, we encourage you to follow our Facebook pages and visit our website regularly. We will continue to share visual updates, progress reports, and any significant announcements related to Fantasea Condo Kamala.<\/p>\n

<\/span>Conclusion<\/h2>\n

The construction of Fantasea Condo Kamala is progressing well, and we are excited about the strides made during the month of May 2023. The piling phase is underway, with substantial completion percentages for both Building A and Building B. We have diligently addressed challenges and remain committed to delivering a high-quality development.<\/p>\n

Thank you for your continued support and trust in our project. We appreciate your patience as we work towards creating a remarkable living space at Fantasea Condo Kamala. Stay tuned for further updates in the coming months as we move closer to realizing our vision.<\/p>\n

Warm regards,
\nTony He
\nCEO
\nFantasea Plus Co., Ltd.<\/p>\n

>> To download full report, please click refers to this link:\u00a0Monthly Report 1-25 May 2023 -FCK<\/a>[\/vc_column_text][\/vc_column][\/vc_row]<\/p>\n<\/div>","protected":false},"excerpt":{"rendered":"

[vc_row][vc_column][vc_column_text]Welcome back to our monthly construction update for Fantasea Condo Kamala! We are excited to share the latest developments and progress made during the month of May 2023. In this blog post, we will provide you with an overview of the ongoing construction activities and updates on the piling phase. […]<\/p>\n","protected":false},"author":1,"featured_media":2751,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[44],"tags":[],"acf":[],"_links":{"self":[{"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/posts\/2750"}],"collection":[{"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/comments?post=2750"}],"version-history":[{"count":1,"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/posts\/2750\/revisions"}],"predecessor-version":[{"id":2756,"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/posts\/2750\/revisions\/2756"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/media\/2751"}],"wp:attachment":[{"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/media?parent=2750"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/categories?post=2750"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/fantaseaplus.com\/wp-json\/wp\/v2\/tags?post=2750"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}